Calcuate Latest Finish Date during work order planning

Latest Finish Date is calculated based on the value visible in the Latest Finish Date Calculation field on the Work Order Plan.

When the user is creating an One-off Work Order - the Latest Finish Date cannot be changed. When the user is calculating Work Order directly from the Work Order Plan card - the Latest Finish Date cannot be changed. When the user is using Planning Worksheet - the Latest Finish Date can be changed - the relevant field is hidden by default.

The Latest Finish Date cannot be set up before the Original Planned Date.

After creating a Work Order - the Latest Finish Date is added to the record. The relevant field is hidden by default.

When the Work Order is closed - the Latest Finish Date is also added to the Posted Work Order.