Right now you can easily update Work Order Plan directly from the Posted Work Order. The update will be performed based on your consumption on the selected posted work order.
You can update:
*if you are using advanced planning or skills - resources can not be updated **only if you are using expenses on plans
+!image-2023-03-07-16-28-39-582.png|width=477,height=236!+
+Important: if you select what you want to update - related data on the work order plan will be DELETED.+
Instructions
Instructions from the posted document are applied to the plan.
Resources
All resources that are consumed are added to the plan. If you select, that you do not want to update resource no. - resource no will be blank after update. If on the posted work order resource is posted without work type code, and you will select that you do not want to update the resource no. - this line will be skipped after update. If the resource on the posted work order line does not exist anymore, or is not maintenance resource right now - its number will be skipped and this field will be blank on the plan.
Items
All items that are consumed are added to the plan. If the item on the posted work order line does not exist anymore, or is not maintenance item right now - its line will be skipped.
Expenses
All expenses that are consumed are added to the plan. If the expenses on the posted work order line does not exist anymore - its line will be skipped.
For all lines: estimated quantity on the work order plan line is set up as the consumed quantity from the posted work order line.
Example
From given example: first three lines came from the plan, but there was no consumption on them. Last three were not planned but added on the work order and consumed. After updating resources on the plan - first three will be deleted on the plan, last three (KC, LM, LP) will be added to the plan with relevant estimated quantity on them.