This article provides a comprehensive guide to configuring the Resource Scheduling Board (RSB) in Dynaway EAM for Microsoft Dynamics 365 Business Central. The RSB is a powerful tool for visualizing, planning, and managing resource assignments for work orders and maintenance activities.
The Resource Scheduling Board enables maintenance planners and supervisors to: - View all scheduled work orders and assignments in a calendar or Gantt chart format - Drag and drop work orders to assign or reassign resources - Monitor resource workloads and availability - Filter and group work orders by asset, location, work type, or other criteria - Quickly identify scheduling conflicts and optimize resource utilization
To open the Resource Scheduling Board: 1. Navigate to the Dynaway EAM menu in Business Central. 2. Select Resource Scheduling Board from the available options. 3. The board displays a timeline view of resources and their assigned work orders.
Follow these steps to configure the Resource Scheduling Board for your organization:
Below are important fields and actions available on the Resource Scheduling Board:
| Field/Action | Description |
|---|---|
| Resource Name | The technician, team, or equipment assigned to work orders |
| Work Order Number | Unique identifier for each scheduled work order |
| Start Date/Time | Scheduled start of the work order |
| End Date/Time | Scheduled end of the work order |
| Status | Current status (Scheduled, In Progress, Completed, etc.) |
| Asset/Location | Asset or location associated with the work order |
| Drag-and-Drop Assignment | Allows manual reassignment of work orders to resources |
| Conflict Indicator | Highlights scheduling conflicts or overlapping assignments |
| Filter/Group Options | Tools to filter and group work orders/resources |
| Timeline Scale | Adjusts the time scale (hour, day, week, month) |
| Color Coding | Visual cues for work order status and priority |
This article explains how individual users can configure their personal settings for the Resource Scheduling Board (RSB) in Dynaway EAM for Microsoft Dynamics 365 Business Central. User-specific setup ensures that each user’s preferences are automatically applied when opening the board, streamlining daily planning and scheduling activities.
Each user can personalize their RSB experience by adjusting filters, display options, grouping, visible objects, and color schemes. These settings are saved and applied automatically, but can be changed at any time.
Note: Some fields may be hidden by default (e.g., Show Lines Caption Boolean).
Many options in the user setup can also be changed directly from the board using dedicated toolbar actions, so you do not need to open the user setup every time.
Basic board setup options include:
| Field | Description |
|---|---|
| Use Dates to Create Board | Defines how the board’s start/end dates are set (True/False) |
| Last Period View Days | Number of days in the past to include in the board view |
| Object Look Ahead | Number of days in the future to include in the board view |
| Starting Date | Exact starting date of the board |
| Ending Date | Exact ending date of the board |
| Show Priority Color | Shows priority bookmark on objects |
| Show Symbols | Shows symbols on the board |
| Show Original Planned Date | Shows line for original planned date |
| Show Latest Finish Date | Shows line for latest finish date |
| Highlight Scope from Original Date | Highlights time scope from original planned date when moving objects |
| Highlight Scope to Latest Finish | Highlights time scope to latest finish date when moving objects |
| Default Filter | Filter created, saved, and set by the user; auto-applied on board open |
*Highlighted scope differs for regular and advanced planning. See the chapter about moving objects for details.
Configure how resources and contractors are displayed and grouped:
| Field | Description |
|---|---|
| Group by | Organizes resources/contractors by None, Group, Responsibility Center, or Work Type |
| Show | Defines what is visible: Resources and Contractors, Resources only, or Contractors only |
If a group (resource or contractor) is not shown, it will not be created on the board, even if selected in setup.
Choose which blocks are shown on the board: - Resource Work Orders - Resource Round Orders - Contractor Work Orders - Maintenance Tasks - Resource Maintenance Absences - Resource Orders Simulations - Resource Rounds Simulations - Maintenance Tasks Simulations
Configure how objects are highlighted and arranged:
| Field | Description |
|---|---|
| Highlight | Which blocks are highlighted (All, Same Source, Overdue) |
| Compress Objects | Reduces objects to one line only |
| Orders Arrangement | Shows orders for the same day next to each other (when advanced planning is off) |
| Show Unscheduled | Shows unscheduled objects (without assigned resource/contractor) |
Unscheduled objects are grouped differently depending on the selected grouping option (None, Group, Work Type, Responsibility Center).
Set up color schemes for resources, orders, tasks, vendors, and contractors:
| Field | Description |
|---|---|
| Resource Color By | Colors resources by group color |
| Order Color By | Source of color for order objects (work orders, round orders, simulations) |
| Maintenance Task | Color for maintenance task objects |
| Vendor Color | Color for vendor groups |
| Contractor Work | Color for contractor work objects |
To edit resource line status, right-click a work order and select Edit Work Order. Enable the Resource Line tab via personalization.
This article explains how individual users can configure their personal settings for the Resource Scheduling Board (RSB) in Dynaway EAM for Microsoft Dynamics 365 Business Central. User-specific setup ensures that each user’s preferences are automatically applied when opening the board, streamlining daily planning and scheduling activities.
Each user can personalize their RSB experience by adjusting filters, display options, grouping, visible objects, and color schemes. These settings are saved and applied automatically, but can be changed at any time.
Note: Some fields may be hidden by default (e.g., Show Lines Caption Boolean).
Many options in the user setup can also be changed directly from the board using dedicated toolbar actions, so you do not need to open the user setup every time.
Basic board setup options include:
| Field | Description |
|---|---|
| Use Dates to Create Board | Defines how the board’s start/end dates are set (True/False) |
| Last Period View Days | Number of days in the past to include in the board view |
| Object Look Ahead | Number of days in the future to include in the board view |
| Starting Date | Exact starting date of the board |
| Ending Date | Exact ending date of the board |
| Show Priority Color | Shows priority bookmark on objects |
| Show Symbols | Shows symbols on the board |
| Show Original Planned Date | Shows line for original planned date |
| Show Latest Finish Date | Shows line for latest finish date |
| Highlight Scope from Original Date | Highlights time scope from original planned date when moving objects |
| Highlight Scope to Latest Finish | Highlights time scope to latest finish date when moving objects |
| Default Filter | Filter created, saved, and set by the user; auto-applied on board open |
*Highlighted scope differs for regular and advanced planning. See the chapter about moving objects for details.
Configure how resources and contractors are displayed and grouped:
| Field | Description |
|---|---|
| Group by | Organizes resources/contractors by None, Group, Responsibility Center, or Work Type |
| Show | Defines what is visible: Resources and Contractors, Resources only, or Contractors only |
If a group (resource or contractor) is not shown, it will not be created on the board, even if selected in setup.
Choose which blocks are shown on the board: - Resource Work Orders - Resource Round Orders - Contractor Work Orders - Maintenance Tasks - Resource Maintenance Absences - Resource Orders Simulations - Resource Rounds Simulations - Maintenance Tasks Simulations
Configure how objects are highlighted and arranged:
| Field | Description |
|---|---|
| Highlight | Which blocks are highlighted (All, Same Source, Overdue) |
| Compress Objects | Reduces objects to one line only |
| Orders Arrangement | Shows orders for the same day next to each other (when advanced planning is off) |
| Show Unscheduled | Shows unscheduled objects (without assigned resource/contractor) |
Unscheduled objects are grouped differently depending on the selected grouping option (None, Group, Work Type, Responsibility Center).
Set up color schemes for resources, orders, tasks, vendors, and contractors:
| Field | Description |
|---|---|
| Resource Color By | Colors resources by group color |
| Order Color By | Source of color for order objects (work orders, round orders, simulations) |
| Maintenance Task | Color for maintenance task objects |
| Vendor Color | Color for vendor groups |
| Contractor Work | Color for contractor work objects |
To edit resource line status, right-click a work order and select Edit Work Order. Enable the Resource Line tab via personalization.