Define if Counter Frequency is triggered as fixed value or relavant to value defined during closing work order

The user can specify if the counter frequency on the Work Order Plan should be calculated from fixed, or actual value.

From given example:

  • choosing a Fixed option, when the Work Order is done, and the user will choose the counter reading on WO - the next triggered value for this WOP will be 300 + 100 so 400
  • choosing an Actual option, when the Work Order is done, and the user will chose the counter reading on WO - the next triggered value for this WOP will be registered/chosen reading + 100 ** choosing/registering the counter reading 315 the next planned counter reading will be 415

Any existing counter frequencies before this new approach are treated as Actual.